Dairy Road Closure Update

Dairy Road south of Hibiscus Boulevard remains closed due to the collapse of the M-1 Canal culvert.  West Melbourne, with engineering assistance from Brevard County, has ordered replacement concrete box culverts, and they are being manufactured off site.  The manufacturer has scheduled deliveries of the twenty-four sections the week of January 22.

Permit applications for the new culvert have been submitted to Brevard County.  The new culvert will be longer than the failed culvert so as to easily allow the roadway to be widened to four lanes in the future without having to modify the drainages.  It is anticipated that the culvert replacement work will commence the end of next week and be completed in late February or early March.